[Q] P is thrice as
good as workman as Q and therefore is able to finish a job in 60 days
less than Q. Working together, they can do it in:
(a) 20 ½ days
(b) 22 ½ days
(c) 21 ½ days
(d) 23 ½ days
(a) 20 ½ days
(b) 22 ½ days
(c) 21 ½ days
(d) 23 ½ days
Solution
Answer
(b)
Explanation
----
If P completes a work in 1 day, Q completes the same work in 3 days
Hence, if the difference is 2 days, Q can complete the work in 3 days
=> if the difference is 60 days, Q can complete the work in 90 days
=> Amount of work Q can do in 1 day= 1/90
Amount of work P can do in 1 day = 3 × (1/90) = 1/30
Amount of work P and Q can together do in 1 day = 1/90 + 1/30 = 4/90 = 2/45
=> P and Q together can do the work in 45/2 days = 22 ½ days
Explanation
----
If P completes a work in 1 day, Q completes the same work in 3 days
Hence, if the difference is 2 days, Q can complete the work in 3 days
=> if the difference is 60 days, Q can complete the work in 90 days
=> Amount of work Q can do in 1 day= 1/90
Amount of work P can do in 1 day = 3 × (1/90) = 1/30
Amount of work P and Q can together do in 1 day = 1/90 + 1/30 = 4/90 = 2/45
=> P and Q together can do the work in 45/2 days = 22 ½ days